Highway 3 Bridge replacement begins March 19


Cars travel over the Highway 3 Bridge over the East Fork of the Des Moines River this past weekend. The bridge will be closed to through traffic for more than seven months beginning next Monday, March 19. Humboldt Independent photo by Kent Thompson.

By Kent Thompson
Humboldt County will be getting a new bridge over the East Fork of the Des Moines River and work will start as early as later this week.
The bridge, 1.8 miles east of the intersection with Highway 169, will be officially closed to through traffic beginning Monday, March 19.
Demolition of the existing bridge and construction of a new bridge is expected to take seven months, with the new bridge open for traffic beginning in early November.
The project calls for replacing the existing 323-foot by 28-foot steel girder bridge with a 364-foot by 44-foot pretensioned, prestressed concrete beam bridge.
The latest traveler information is available anytime through the state’s 511 system. Visit 511ia.org; call 511 (within Iowa) or 1-800-288-1047 (nationwide); stay connected with 511 on Facebook or Twitter (find links at https://iowadot.gov/511/511-social-media-sites); or download the free app to your mobile device.
To read more about this story, see this week's Humboldt Independent. Don't miss an issue, subscribe now! Just click on the link at the top of this page. Read updates and reader comments by liking Humboldt Newspapers on Facebook.