Taft Street sewer project nearing completion

Tue
03
Nov

Taft Street sewer project nearing completion

Humboldt council hears audit report

By PHIL MONSON
According to a report at Monday’s Humboldt City Council meeting, the Taft Street sanitary sewer improvement project is nearing completion.

Nick Frederiksen of ISG Engineering of Des Moines, and Ryan Miller of PeopleService, gave an in-depth report at the council meeting on Nov. 2. Their reports preceded the council’s approving a first phase payment of $$146,421.26 on the project.

With the completion date of Nov. 15 just around the corner, Frederiksen said favorable weather conditions are a must for the project to be completed.

“We held a project meeting on Oct. 28 and went through all the work they have gotten done through today. Amy (Zeman, city administrator) and Walter (Jensen, mayor) were the along with Ryan Miller,” Frederiksen said.